The first sign is rarely a letter. It is a payment that lands short with no pay less notice to explain it. Then a payment that lands late. Then a quantity surveyor who used to pick up the phone and now does not. By the time the administrators' notice arrives, the people who were paying attention have already worked out what is happening. The question is what they did about it in the weeks before.
Construction is the industry's insolvency specialist. In the twelve months to 30 September 2026 the Insolvency Service recorded 3,873 company insolvencies in construction, 17 per cent of all cases where the industry was captured, which makes it the largest sector by a distance. Most of those were not the household names. They were businesses the size of yours, and a good proportion of them took somebody else's money down with them. So this is not a piece about whether your contractor might fail. It is about what the contract already lets you do when the signs appear, and why the order in which you do it matters.
The signs, and why they are not neutral
Nobody announces insolvency. It leaks. Short payments without a pay less notice. Notices that arrive but say less each month. A request to re-phase your applications, or to invoice a different entity, or to hold off on the next one "while the client sorts their drawdown". A main contractor still winning new work while its existing supply chain goes unpaid, which happens more often than it should. A site that quietly thins out.
None of those are proof of anything, and most businesses have a bad month. But they are information, and the common mistake is to treat them as somebody else's problem. A contractor that is not paying you on time is already using your money as working capital. The only question is whether it gives it back. Every week you spend being understanding is a week in which your exposure grows and your options shrink.
The payment regime does not stop
The Construction Act keeps running right up to the moment of appointment, and so should you. Serve every application on the contractual date, in the contractual form, showing the sum and the basis. If the payer serves no payment notice, your application stands as the notified sum. If it serves no pay less notice, that sum is payable in full by the final date. We set the whole timetable out in the five days that decide the month, and a contractor in difficulty is precisely the one most likely to miss its notices, because the people who used to serve them have other things on their minds.
That gives you a clean, unarguable debt, which is the thing you want in your hand before any of what follows. A disputed valuation is a negotiation. A notified sum unpaid after the final date is a debt. Make sure you are holding the second kind.
A contractor that is not paying you on time is already using your money as working capital. The only question is whether it gives it back.
Suspend, properly
If a notified sum is not paid by the final date, the Act gives you a statutory right to suspend performance. It is not a right to walk off. It is a right exercised by notice, of at least seven days, stating the ground, and it continues until payment is made. Used correctly it is powerful: it stops you pouring more unpaid work into a business that may not be there next month, it changes the conversation at the top of the chain, and the time you lose is dealt with by the Act rather than counted against you.
Used incorrectly it is a disaster. Downing tools without the notice, or on the wrong ground, or before the final date has passed, is not suspension. It is a breach, and quite possibly a repudiation, and it hands a struggling contractor the one thing it would love to have, which is a claim against you. Read the clause, serve the notice, keep the proof of service, and do not leave site until the period has run.
Adjudicate before the collapse, not after it
Adjudication is quick, and speed is the whole point here. A referral today can produce a decision in four weeks. The thing to understand is what that decision is worth on either side of an appointment.
Before the contractor goes into an insolvency process, an adjudicator's decision in your favour is enforceable and the money, once paid, is yours. After it, the picture changes. Your decision is a claim in the insolvency like any other unsecured creditor's claim, and the courts are understandably reluctant to order an insolvent company to pay out sums that may have to be repaid once the parties' wider accounts are settled. The practical lesson is blunt. If you are going to adjudicate, do it early, while there is still a solvent company to pay, and press for payment the day the decision lands. A decision obtained a fortnight after the administrators arrive is a well-drafted proof of debt.
The one time pay-when-paid works
We have said before that pay-when-paid clauses are generally ineffective under section 113 of the Act. Now the exception, because this is where it lives. The section makes such a clause ineffective "unless that third person ... is insolvent". So where the client above your contractor has failed, and your sub-contract contains a properly drafted pay-when-paid provision, your contractor may lawfully withhold what it has not received. Two things follow. Check whether your sub-contract contains such a clause at all, because many do not and a contractor cannot rely on one that is not there. And if it does, understand that the risk of the client's failure sits with you for exactly as long as that clause does, which is a point to raise before you sign the next one.
Retention, materials and the things you thought were yours
Three assets are at risk in the weeks before an appointment, and all three are better protected early than late.
- Retention. Unless the contract required it to be held in a separate trust account and that account was actually set up, your retention is a book entry in the contractor's ledger and you are an unsecured creditor for it. We wrote about this in retention is your money. Apply for it formally, as soon as the trigger is met, and if you have a right to require a trust account, this is the moment to use it.
- Unfixed materials. Materials on site that you have not been paid for are a classic casualty. Read your retention of title terms, read what the contract says about when title passes, and be aware that once materials are built in, arguments about who owns them are largely over. Do not deliver ahead of need to a site you have doubts about.
- Plant and equipment. Keep an inventory of what is yours on site, labelled and recorded. The administrators' first job is to secure the site, and an unlabelled compressor in a locked compound is a long conversation.
A decision obtained a fortnight after the administrators arrive is a well-drafted proof of debt.
Termination: read the clause before you act on it
Most forms let a party terminate on the other's insolvency, and define carefully what counts as insolvency for that purpose. Use the clause, not your instincts. Terminating on a ground the contract does not recognise, or before an event the contract defines has actually occurred, is a breach dressed up as a remedy. And remember the clause is mutual. The contractor can terminate on your insolvency too, which is one more reason to keep your own cash position honest while you are chasing theirs.
Expect approaches from above. Employers sometimes offer to pay sub-contractors directly, or to novate the package, to keep the project moving. These can be good outcomes. They are also agreements that need to be documented properly, with the existing debt dealt with expressly rather than left to assumption, so take advice before you sign anything that says "fresh start".
What good looks like
The businesses that come out of a contractor's insolvency with the least damage are the ones that did a small number of things, early:
- They treated the first short payment as a signal, not a nuisance, and looked at their total exposure to that contractor across every job the same week.
- They kept serving applications on the contractual dates, so every month produced a notified sum rather than an argument.
- They suspended by notice when the Act allowed it, and not a day before.
- They adjudicated on clean debts while the counterparty was still solvent, and chased payment of the decision the day it arrived.
- They applied for retention the moment the trigger was met, and pressed for a trust account where the contract allowed one.
- They kept the record: every application, every notice, every delivery ticket, every inventory, in one place, ready for the administrators' first request.
None of it is clever. All of it is the kind of thing that gets skipped when a business is busy and the contractor is a long-standing customer who has always paid in the end. Until the month it does not.
The contract already knows what to do
There is no mystery to any of this. The Act and the contract between them set out the notices, the rights and the order of events. The difference between a sub-contractor that recovers most of what it is owed and one that recovers almost nothing is rarely the law. It is whether, in the three or four weeks when the signs were there and the company was still solvent, somebody read the clause and served the notice. By the time the administrators write to you, that window has closed. Everything that follows is a proof of debt and patience.
The weeks before an appointment are a notices problem, and notices are what Defender Platform is built to manage. It keeps every application and final date on one calendar, tells you the day a payment notice has not arrived, and holds your exposure to each counterparty across every live contract in one view, so the first short payment is a number you can see rather than a feeling you have.